DESCRIPTION: Provided four 4 story exterior steel stair structures with ¼” plate guard rails, concrete cast in place treads, metal breezeway rails, metal deck floor connecting two buildings. Masonry to …
Benchmark Electronics
DESCRIPTION: Fabrication and erection of office buildings. Concrete tilt panel design with structural steel framing, steel joist, stair framing with railing, screen wall framing, and canopies. 66,196 sq ft 2 story …
Tesla Building A Prime Facility
DESCRIPTION: Fabrication only: The total steel package contains 9000 tons of steel. Bell Steel fabricated 3000 tons of the steel package. LOCATION: Sparks, NV
Arizona State University Student Pavilion
DESCRIPTION: Fabrication and erection of new 3-story student pavilion including 850 tons of steel, canopies, stairs, and metal decking. The project included (4) 104’ trusses that weighed 30 tons each. …
Arizona State University Biodesign Institute
DESCRIPTION: Fabrication and erection of new construction 5-story research facility. Scope included structural steel, steel decking, 2-interior stair towers plus 1-lobby stair (delegated design). Also performed miscellaneous metals, partition supports, site …
Phoenix Children’s Hospital Emergency Department Expansion
DESCRIPTION: Bell Steel’s scope included structural materials, floor and roof deck, steel stairs, and fabrication only for the new 3-level hospital addition. First Floor – Emergency Department, Second Floor- Administration Offices, …
Chaparral Commerce Center
DESCRIPTION: Fabrication and erection of office buildings. Concrete tilt panel with steel joist roof, heavy steel 2nd floor framing, bridge between buildings, steel decking, stairs, railings and canopies. 275,000 sq ft …
Grand Canyon University Baseball Stadium
DESCRIPTION: Fabrication and erection of structural steel for the metal deck canopy roof super columns and miscellaneous handrails, guardrails, and gates for 3,500 seat grandstand stadium totaling 58,566 square feet …
Girl Scouts Camp Sombrero
DESCRIPTION: Fabrication and erection of 15 cabins, 2 leadership buildings, 2 activity buildings, and 1 volunteer building totaling 40,488 square feet and approximately 550 tons of steel. LOCATION: Phoenix, AZ
Grand Canyon University Soccer Stadium
DESCRIPTION: Fabrication and erection of structural steel for the canopy roof and miscellaneous handrails, guardrails and gates for 3,200 seat grandstand stadium totaling 41,852 square feet with approximately 650 tons of …
- Page 2 of 2
- 1
- 2